Home » Project Information » Current Work » Drilled Shaft and Driven Pile Test Project
Drilled Shaft and Driven Pile Test Project
Click on the above map to see full sized PDF.
Two foot diameter shaft during pile installation on March 29, 2012 in Oregon. When completed, the pile will be 131 feet deep.
The Columbia River Crossing (CRC) project will conduct a construction
techniques test project in March 2012. Through this research, CRC will evaluate
the strength of the soil and the construction techniques for the replacement
Interstate 5 bridge support structures. Construction noise and vibration effects
at nearby residences and businesses also will be evaluated. The work will allow
engineers to refine design assumptions and project plans, ensuring the
construction phase for the CRC project stays on schedule and on budget.
The work will occur at two on-land locations just west of I-5 near
the I-5/State Route 14 interchange in Washington and the Hayden Island
interchange in Oregon. The locations were chosen to represent a range of soil
conditions and required foundation depths for the CRC bridges.
Any necessary night work will conform with applicable city noise ordinances.
Construction on the test project is scheduled to be complete by summer 2012.
Why is this test project being conducted?
This test project will help engineers evaluate:
- Soil strength and construction techniques for drilled
shafts and driven piles
- Noise and ground vibration levels produced by pile
driving at different locations and distances
- Installation methods to ensure the construction phase of
the replacement I-5 bridge stays on schedule and on budget
- Methods and procedures to help ensure foundation work
will not diminish groundwater quality
What are drilled shafts and driven piles?
Drilled shafts are deep, cylindrical holes into which concrete is poured for
bridge foundations.
A pile is a long, cylindrical steel column that is driven
into the soil to provide support for bridges and other
structures. Installation of driven piles can create noise
associated with metal striking metal.
What specific work is being done?
Construction crews will install a total of three drilled shafts and five
piles at two locations just west of I-5 near the I-5/State Route 14
interchange in Washington and the Hayden Island interchange area in Oregon. The three drilled shafts for this test project will measure 6 feet, 8 feet and 10 feet in diameter and will be installed 130 feet, 160 feet and 260 feet below ground level.
Noise and vibration levels on land will be monitored on
Hayden Island before and during testing to assess the effects of
the driven pile installation in the nearby communities. A
minimum of three noise monitors and six vibration monitors will
be used to measure effects of the test project. (See map for
locations.) Test pile driving will not occur in Vancouver.
What should I expect to see and hear?
The test project will resemble a construction project and
large cranes will be visible in the work areas just west of the
I-5 bridge. Temporary, chain-link fencing will be placed around
the work zones.
There will be a combination of sounds associated with driving
piles. The noise heard will depend on the surrounding
topography, buildings, wind and other noise. Noise associated
with the test might be heard intermittently for up to a few
hours a day during the study. Other sounds typically associated
with construction include heavy equipment, trucks and truck
back-up beepers, an Occupational Safety and Health
Administration (OSHA) requirement.
When will the test project occur? How long will it last?
The test project is expected to begin mid-March. The project could take up to 14
weeks to complete with work occurring in daytime and night-time hours. All work
is expected to be complete by summer 2012.
How can I get more information?
Email: feedback@ColumbiaRiverCrossing.org
Related Materials